How long a whole house remodel takes depends mostly on what happens before construction starts, but most of the ones Dreamstead Builders does around Austin run 6 to 12 months from the first walkthrough to move-in. Construction is usually 4 to 8 months of that, and design and permits make up the rest. Those are typical numbers from our experience, not a promise, and below is what pushes a whole home remodeling project toward the short end or the long end.
How long does a whole house remodel take, phase by phase
A whole house remodel moves through five phases, and each one has its own typical length and its own usual reasons for running long. Here’s how they line up on the projects Dreamstead Builders runs in Austin, Round Rock, Lakeway and the rest of the metro.
| Phase | Typical in our experience | What usually stretches it |
|---|---|---|
| Assessment, planning and design | 1-3 months | Layout changes, engineering, selections still open |
| Permitting | Varies by jurisdiction | Review comments, incomplete drawings, historic review |
| Demolition | 1-3 weeks | Rot, old wiring, foundation movement |
| Structure, rough-in and inspections | 1-3 months | Foundation repair, inspection corrections, weather |
| Finishes and final walkthrough | 2-4 months | Long-lead materials, change orders |
The phases overlap a little. We’ll often order windows and cabinets while permits are still in review, for example. But you can’t skip a phase, and you can’t really shorten one by leaning on the next.
Planning and design: where the schedule is really set
Planning and design typically takes 1 to 3 months, and it’s the phase that decides whether everything after it runs on time. Dreamstead Builders starts by walking the house with you, checking the structure and the electrical, plumbing and HVAC, and agreeing on what the finished house needs to do. From there come drawings, engineering wherever walls or loads change, and selections.
Selections are the part people underestimate. Every faucet, tile, cabinet door, light fixture and appliance has to be picked, and on a whole house that’s hundreds of decisions. We push hard to lock them before demolition, because a tile that’s still undecided in month four is a tile that might be on backorder when you finally choose it.
What drags this phase out is change. Moving a bathroom after the drawings are underway means new plumbing drawings and sometimes new engineering. Taking out a load-bearing wall means an engineer has to design the beam, and that has its own turnaround. And if two people in the house haven’t agreed on the plan yet, it’s far cheaper to settle that at the kitchen table than in the middle of framing.
Permits: the one phase nobody fully controls
Permitting doesn’t have a fixed length, because the review happens on the city’s schedule, not ours or yours. A whole house remodel with structural, electrical, plumbing and mechanical work needs permits from the City of Austin or whichever jurisdiction the house sits in, whether that’s Georgetown, Pflugerville, Bee Cave or somewhere else. Dreamstead Builders handles the applications and the inspections.
Here’s what the process involves. We submit the drawings and supporting details. Reviewers go through them and often come back with comments: a question about a beam, a missing detail, a note on how something meets code. We answer the comments and resubmit, and once the permit is issued, demolition can start. Review times differ from one city to the next and shift with how busy the office is, so when we price your project we’ll tell you what we’re seeing at that moment instead of quoting a number that may be stale by the time you apply.
Two things reliably stretch this phase. Incomplete drawings earn comments and a second round of review, which is why we’d rather spend an extra week getting the set right. Location matters too. In older Central Austin neighborhoods such as Hyde Park, some homes sit in historic districts that can require additional approvals before the building permit, and that adds time. If your house is one of them, our historic restoration work starts with that review.
Demolition: the week the house tells you the truth
Demolition usually takes 1 to 3 weeks on a whole house, because tearing out is much faster than building. What makes it matter is what you find. Once the drywall and old flooring are gone, Dreamstead Builders can finally see the framing, the wiring and the subfloor, and that’s when hidden problems show up.
In Austin homes, opening the walls commonly turns up things like:
- Rot around old windows, tubs and exterior doors where water got in for years
- Original wiring, especially in homes built before 1980, which often need an electrical panel upgrade
- Supply and drain lines that are past their useful life
- Sloped floors from a foundation that has moved on expansive clay soil
- Thin insulation, or none at all
Most of these don’t move the schedule much. A few rotted studs get replaced in a day. Foundation repair is different: it has to be assessed, sometimes engineered, and finished before the new framing goes in, and it can add weeks. Older houses may also need testing for materials like asbestos or lead paint before certain work begins. That’s why we build a little slack into the schedule right after demo instead of pretending a 60-year-old house in Travis Heights or Brentwood will hold no surprises.
Structure, rough-in and inspections
Structural work and rough-in typically take 1 to 3 months, and they end with inspections that have to pass before any wall gets closed up. This is when the new layout gets framed, beams go in where walls came out, and the plumbers, HVAC crews and electricians run everything that will live inside the walls and ceilings.
Order matters. Framing comes first. Plumbing usually goes next because drains and pipes are the least flexible, then ductwork, then electrical, which can route around the others. Each trade’s rough-in gets inspected, and the inspector has to sign off before insulation and drywall go up.
What stretches this phase is waiting. Waiting on an inspection date, waiting on corrections after an inspection doesn’t pass, waiting on an engineer when something in the field doesn’t match the drawings. Weather plays a part when the roof or exterior walls are open, and an Austin spring storm can cost a few days of outside work at a time. Dreamstead Builders coordinates every trade and calls for inspections as soon as each rough-in is ready, because a crew standing around waiting on the next step is how a week quietly disappears.
Finishes: the longest stretch on site
Finishes typically take 2 to 4 months, which surprises people who expect the end of a job to move fast. Drywall gets hung, taped, mudded and sanded in coats. Then cabinets, countertops, tile, flooring, trim, paint, plumbing fixtures, lights and appliances go in, mostly one trade after another in the same rooms.
Each step waits on the one before it. Countertops can’t be templated until the cabinets are set. The tile setter needs the shower valves in place. Painters want the trim finished. On a whole house that chain runs through the kitchen, every bathroom and every bedroom, so Dreamstead Builders plans the finish sequence as carefully as the structural work.
Long-lead materials and change orders are what stretch finishes most. Custom cabinetry, special-order tile, windows and some appliances take time to arrive, so we order them as early as we can, often while permits are still in review. Change orders hurt most at this stage, because swapping a tile after the setter has started or moving a light after drywall means tearing out finished work. The phase closes with final inspections and a walkthrough with you before handover.
Why two remodels of the same size finish months apart
How much of the house changes matters more to the schedule than its square footage. A 1,500 sq ft ranch in Pflugerville that keeps its layout and gets new systems and finishes will usually finish well ahead of a 2,500 sq ft home in Westlake Hills where walls move, a bathroom gets added and the kitchen relocates. Both are whole house remodels, but one is mostly finish work and the other is mostly construction.
When Dreamstead Builders estimates how long a project will take, these are the things we look at first:
- How much structure changes, including walls, beams and roof lines
- The age and condition of the house, especially wiring, plumbing and any foundation movement
- Whether plumbing moves, since keeping kitchens and baths where they are saves real time
- Which jurisdiction reviews the permit, and whether historic review applies
- How custom the finishes are, and how long they take to arrive
The same things drive the budget. Our Austin remodeling costs guide lays out the published price ranges.
What actually keeps a remodel on schedule
The biggest thing you can do to keep a whole house remodel on time is make decisions early and stick with them. Dreamstead Builders runs the crews, the inspections and the ordering, but your choices set the pace in design and again in finishes.
Finish your selections before demo starts. Approve long-lead items as soon as they’re chosen so they can be ordered. Expect something behind the walls in an older house, and leave room for it. And if you’re timing a lease or a move, plan around the long end of the range, not the short end.
If you’d like a timeline for your own house instead of a typical one, get in touch with us or call (512) 559-6966. We’ll meet you at the property by appointment, walk the house with you, talk through how long your project is likely to take, and follow up with a written estimate.